Paving Program

Paving schedule

This is the StreetsDOT weekly paving operations schedule. Check for posted “No-Parking” signage on these listed streets for updates on when work will take place.

Jump to see information about:


Scheduled paving work

Schedule for: May 11 to May 17

Street From To Work type
Cecil B. Moore Ave. N 23rd St. N 33rd St. Milling
Cottage St. Tyson Ave. Longshore Ave. Paving
Cottage St. Longshore Ave. Knorr St. Paving
Eastwood St. Tyson Ave. Knorr St. Paving
Eastwood St. Knorr St. Unruh Ave. Paving
Eastwood St. Unruh Ave. Magee Ave. Paving
Longshore Ave. Rowland Ave. Frankford Ave. Paving
Longshore Ave. Frankford Ave. Torresdale Ave. Paving
Magee Ave. Roosevelt Blvd. Bustleton Ave. Paving
Magee Ave. Bustleton Ave. Large St. Paving
Magee Ave. Large St. Castor Ave. Paving
St. Vincent St. Hawthorne St. Sackett St. Paving
Tyson Ave. Loretto Ave. Castor Ave. Paving
Unruh Ave. Roosevelt Blvd. Harbison Ave. Paving
Unruh Ave. Harbison Ave. Bustleton Ave. Paving
Unruh Ave. Bustleton Ave. Large St. Paving
Unruh Ave. Large St. Castor Ave. Paving
W Susquehanna Ave. N Front St. N Broad St. Paving

What residents need to know

  • Street resurfacing work happens in four phases: Milling, utility adjustments, paving, and line striping. Learn about the paving process.
  • Before Milling work begins, bright orange door hangers are distributed to nearby residents and businesses.
  • Posted “No Parking” signs will list specific dates when road work is expected to occur.
  • Residents should continue checking for updated no-parking signs throughout all four phases of the street resurfacing process.

Relocated vehicles

For information about a vehicle that was relocated due to road work, contact your local Philadelphia Police District.


Upcoming paving work

See a map of all active and planned paving work on StreetSmartPHL under the PavePHL tab.