Logan Square Sidewalk Improvement

Sidewalk, storm drain, and ADA ramp improvements in Logan Square Park. Current project status: Completed

Jump to:

Background

Overview

Logan Square is an iconic and historic park in Center City Philadelphia that receives thousands of visitors every year and connects many key landmarks. This project focused on Logan Circle, at the center of Logan Square Park. Improvements to traffic safety and accessibility will benefit Logan Square residents, visitors, and everyone attending events along the Benjamin Franklin Parkway. The newly reconstructed sidewalks around Logan Circle feature more durable granite curb as well as color dyed concrete to compliment the gravel paths within Logan Circle.

While Logan Circle was closed during construction, Philadelphia Parks and Recreation (PPR) also completed work on the Swann Fountain and nearby landscaping.

Completed work

  • The 15-foot-wide outer sidewalks of Logan Circle were reconstructed.
  • The new 2,000 square yard sidewalk was constructed using over 366 cubic yards of concrete, roughly 53 concrete trucks.
  • The concrete is dyed a warm tan color to compliment the gravel paths within Logan Circle.
  • New, more durable, granite curb replaced the previous concrete curb.
  • 6 new, larger, storm drains were installed and connected to the sewer.
  • 8 curb ramps were upgraded to current ADA standard designs.
  • Painted traffic markings were refreshed, including 14 crosswalks
  • New landscaping around Logan Circle near the sidewalk was completed to restore the construction site.

Project team

  • Streets Department of Transportation (StreetsDOT)
  • C. Abbonizio Contracting and subcontractors
  • Roma Concrete
  • Traffic Planning and Design (TPD)
  • Philadelphia Parks and Recreation (PPR)

Partners

  • The Parkway Council

Funding

Federal funding from the Federal Highway Administration (FHWA).

Contact

If you have questions, email streets@phila.gov.


Timeline

Current project status: Completed
1
Planning: Completed
2
Design: Completed
3
Construction: December 2025 to May 2026
4
Complete: May 2026

Photos

Standing on the new sidewalk near one of the new ADA ramps looking southeast down the Parkway. The new concrete sidewalk is a warm tan color, rather than normal concrete gray.
The 15 foot wide sidewalk around Logan Circle has been reconstructed including new ADA curb ramps. (Credit StreetsDOT, May 2026)
One of the new storm drains photographed during construction with the ground around it excavated. The drain features a black painted metal grate on top of a large concrete box set into the ground. A large pale red pipe connects to the side of the concrete box and continues underground.
New storm drains roughly double the size of the previous ones were installed around Logan Circle before replacing the sidewalk. (Credit StreetsDOT, December 2025)