PHILADELPHIA — The Streets Department of Transportation (StreetsDOT), Schuylkill River Development Corporation (SRDC), Pennsylvania Department of Transportation (PennDOT), as well as Local and State officials cut the ribbon and opened the Schuylkill Crossing Swing Bridge. This new bridge creates a high-quality trail connection between South and Southwest Philadelphia, filling a vital gap in the Schuylkill River Trail (SRT) by linking the larger trail to an additional 1.5 miles through Bartram’s Garden and ending just north of 61st Street.

“We are connecting Philadelphia to park space, healthy active recreation, safe off-street transportation, and our city’s own history“, said Carlton Williams, Managing Director. “Whether it’s a new car-free commute, after work run, or weekend adventure for the kids. Making Philadelphia safer, cleaner, and greener, with economic opportunity for all, starts by creating new and convenient options for everyone to participate.”

This type of bridge is not only new to Philadelphia, the Schuylkill Crossing Swing Bridge is the only operational swing bridge dedicated to trail use in the nation. The new bridge reuses historic components of the previous train bridge donated by Conrail, PBW&B Bridge No. 31, including the center pier and approach spans. Using this foundation, a new swing truss, machinery, approach span floor beams, concrete decks, railings, lighting, and fender system were added. The new swing truss is smaller and lighter than the previous rail crossing, designed and constructed specifically for trail users.

The project started with a stakeholder meeting in November 2009 that assessed the project’s critical parameters. From this initial meeting, SRDC and their design consultant WSP explored multiple bridge concepts that would restore the river crossing. This included options to construct a prefabricated truss, a cable-stayed structure, or rehabilitate the preexisting railroad truss.

“The opening of Schuylkill Crossing continues the decades-long transformation of Philadelphia’s lower Schuylkill River into a premier riverfront destination that connects more people to more places and recreation along the river.” said Heather Saegar, Interim CEO of Schuylkill River Development Corporation. “I am proud of SRDC’s enduring partnerships with the City of Philadelphia and the Schuylkill Banks community, whose expertise and dedication to completing this complex trail project has delivered long-term and substantial benefits to nearby neighbors, the greater Philadelphia region, and the Commonwealth.”

The project team includes SRDC who managed the planning and design phases, with design work completed by WSP (formerly Louis Berger, formally Ammann & Whitney) and Hardesty & Hanover. The StreetsDOT Construction Unit managed the construction phase, with construction management and inspection services provided by Urban Engineers, Gresham Consulting, and Michael Baker International, with work completed by A.P. Construction and their subcontractors. StreetsDOT’s Transportation Planning and Analysis unit as well as other City teams including the Law and Procurement departments, were essential to project management. FHWA and PennDOT funded the project and were active and indispensable partners.

“Throughout construction, the project team has focused on delivering the highest-quality product for the city,” said Kristin Del Rossi, Streets Commissioner. “Taking time to complete this project ensures a dependable bridge that operates as intended the first time, fiftieth time, and five-thousandth time. This is a unique transportation asset to Philadelphia’s world-class trail network, today and for future generations to come.”

The construction of the Schuylkill Crossing Swing Bridge cost approximately $28 million, including local, state, and federal funds. The final project total is still being determined with work on the project continuing after the bridge and trail have been opened to the public.

The project included many notable engineering and construction highlights, such as the assembly of the swing truss and pouring of the concrete bridge deck. The swing truss was delivered to the project site by truck in 12 flat truss panels with corresponding cross members. These components were then assembled into six truss sections on land. These truss “boxes” were then loaded onto a barge and floated upriver to where they could be lifted into place on temporary supports above the center pier fender system. Each half of the truss is composed of 3 sections, plus a center “keystone” section that holds everything together. Once assembled in the middle of the Schuylkill River, pouring the concrete bridge deck was a unique operation. The deck of the new truss uses lightweight concrete and was constructed in one continuous pour. Concrete truck deliveries were staged on the nearby Grays Ferry Avenue Bridge. The concrete was then pumped from Grays Ferry Avenue to the Swing Bridge via approximately 300 feet of pump hose and slick line, with slick line segments gradually removed as the pour progressed from south to north.

“There’s a phrase often said in heavy highway construction: ‘we aren’t building a Swiss watch’, meaning fractions of inches can be made up in concrete to little consequence, “ said Tyler Barile, Assistant Chief Construction Engineer, StreetsDOT Construction Unit. “But I would argue that this bridge has more in common with a Swiss watch than it does with a standard highway bridge. Some of the machinery here is calibrated to tolerances in hundredths or even thousandths of inches.”

The machinery that powers the swing bridge includes precise components manufactured across the United States, brought together and assembled atop the historic bridge piers.

  • Motors from Reuland Electric Motor Co. In City of Industry, California
  • Reducer Gearboxes from Nuttal Gear in Niagara Falls, New York
  • Turning Machinery from JC Machine, Miami, Florida
  • Electrical Control Equipment from Panatrol Electric in Oak Forest, Illinois
  • Swing Truss Structure from Pelet Welding in Coatesville, Pennsylvania

The Schuylkill River, up to the Fairmount Water Works, is a navigable waterway controlled by the United States Coast Guard. With the swing bridge’s vertical clearance of 26-feet and 1-inch above mean high tide, the bridge is required to open to allow for taller maritime vessels to traverse the navigable Schuylkill, when needed. The unique proximity of the swing bridge and Grays Ferry Bridge led to the creation of a new US Coast Guard maritime navigational lighting standard when considering close-proximity movable and fixed bridges. The navigational lighting on the two bridges is synchronized to provide clarity to maritime traffic. When the swing bridge is in the “closed” position, navigational lights on the truss denote the channel as “closed.” When the swing bridge is on the “open” position, the green navigational lights on the Grays Ferry Bridge are illuminated to signify an open channel.

The frequency with which the Swing Bridge will need to be opened, and the trail temporarily closed, will fluctuate with river traffic demand. StreetsDOT anticipates brief monthly closures to inspect and exercise the swing bridge’s machinery. Opening the bridge for maritime traffic is done by appointment and coordinated with the US Coast Guard.

The first recorded river crossing at this location was a local ferry operated by Benjamin Chambers in the 1600s and early 1700s. This was before George Grey took over and established Grey’s Ferry in 1747. The first bridge built here was a pontoon bridge in 1777. The pontoon bridge was washed away several times before The Newkirk Viaduct was built in 1838, the first permanent railroad crossing at the location. In 1902 the American Bridge Company built the original swing bridge, PW&B Bridge No. 31, replacing the viaduct. That bridge was acquired in 1976 by Conrail and removed from regular service. Only eight years later the rail line on the bridge was abandoned. In 2017 Conrail gave ownership of the bridge structure to the City, and a year later construction began to convert the crossing into part of Philadelphia’s trails network.

“This bridge connects more than two riverbanks. It brings the Schuylkill River Trail into neighborhoods that haven’t always shared in the city’s great public spaces, and it shows that industrial land and public recreation can thrive side by side.“ said Jodie Harris, President of PIDC. “As the City’s economic development corporation, PIDC is proud to have assembled and prepared the land that made this stretch of trail possible, and to continue that work alongside the City and SRDC.”

Now, this river crossing enters a new era as an essential part of Philadelphia’s world class trail network, the regional Circuit Trails network, and the national East Coast Greenway.

Shared, public, outdoor space strengthens our communities,” said Susan Slawson, Parks and Recreation Commissioner. ”This project goes above and beyond in connecting neighborhoods, unlocking new options for commuting and recreation, and introducing institutions like Bartram’s Garden and Schuylkill Banks to more people.”

“The Schuylkill Crossing bridge opens an extraordinary new chapter for Southwest Philadelphia and our relationship with the Tidal Schuylkill River,” said Maitreyi Roy, Executive Director Bartram’s Garden. “For neighbors, it creates a long-awaited connection to Center City and the regional trail network, opening new possibilities for commuting, recreation, and discovery. And we look forward to welcoming everyone to experience the beauty of nature and discover the rich history and stories of this extraordinary stretch of the Tidal Schuylkill.”

“The new swing bridge over the Schuylkill River is a giant leap forward for connectivity and community in Philadelphia,“ said Dennis Markatos-Soriano, Executive Director East Coast Greenway. “It’s also a giant leap forward for the entire Maine to Florida East Coast Greenway, a trail connecting cities from Boston, New York, and Philadelphia to Washington DC, Charleston, and Miami. Together, we are building miles of smiles that improve health, sustainability, and affordability for everyone in our 3,000-mile corridor.”

Today’s celebration of the city’s newest public river crossing recognizes the vital role that transportation infrastructure plays in the social, health, and economic improvement of Philadelphia. The Schuylkill Crossing Swing Bridge creates new opportunities for everyone, residents and visitors, whether they are entertaining their children, exercising, traveling to an event, or commuting for work.

Project Details:

  • 415-foot-long bridge consisting of two 95-foot approach spans and the 225-foot-long center truss span.
  • Both approach spans are rehabilitated historic structures from the existing train swing bridge. This includes the abutments, piers, and structural steel. New concrete decks, floorbeams, railings, lighting, and end lift machinery were added.
  • The center pier, underneath the new swing bridge machinery and center truss, is also historic and original to the previous train swing bridge.
  • The project also included new asphalt trails leading to the bridge, a new stairway with bike runnels, trail lighting, and landscaping including stormwater drainage and a bioswale.
    0.6 miles of new trail, including the swing bridge. The new trail varies in width between 10 and 12 feet. Additionally, the center of the bridge features a wider circular viewing area.
  • The project fills a gap in the SRT by connecting it to 1.5 miles of preexisting trail segments in Southwest Philly to the larger trail upriver. This brings the total length of the Schuylkill Banks section of the trail to 4.7 miles. The total uninterrupted length of the SRT in Philadelphia is now 9.5 miles between Ridge Avenue at Wissahickon Creek and the southern terminus of the trail near 61st Street.

Project Team:

  • Streets Department of Transportation (StreetsDOT)
  • A.P. Construction Inc. (Prime Contractor)
  • Urban Engineers (Construction Management/Construction Inspection Services)
  • Gresham Consulting and Michael Baker International (City’s Consulted Mechanical Expert)
  • Schuylkill River Development Corporation (SRDC)
  • WSP and Hardesty & Hanover (Designers)

Funding:

  • Federal Highway Administration (FHWA)
  • Pennsylvania Department of Transportation (PennDOT)
  • Pennsylvania Commonwealth Financing Authority (CFA)
  • Delaware Valley Regional Planning Commission (DVRPC)
  • City of Philadelphia
  • Schuylkill River Development Corporation (SRDC)
###