Temporary, Full Street Closures and Parking Restrictions Expected

PHILADELPHIA – Streets Commissioner Kristin Del Rossi announced today that temporary street closures and parking restrictions to accommodate street milling in the 4th Highway District for the week of September 9, 2024. (Day work)

Between September 9th and 13th, the contractors expect to complete milling on the following streets:

On Street From Street To Street
 TULPEHOCKEN ST LOWBER ST RODNEY ST
WOODBROOK LN CRITTENDEN ST STENTON AVE
ROUMFORT RD  CRITTENDEN ST MANSFIELD AVE
CRITTENDEN ST WOODBROOK LN E TULPEHOCKEN ST
ALLENS LN SPRAGUE CRITTENDEN ST
E SEDGWICK ST ARDLEIGH ST STENTON AVE
E GORGAS LN  ARDLEIGH ST STENTON AVE
VERNON RD ARDLEIGH ST CRITTENDEN ST
ARDLEIGH ST E UPSAL ST E GORGAS LN
MILTON ST VERNON RD GORGAS LN
ANDERSON ST E SEDGWICK ST W WASHINGTON LN
GORSTEN ST VERNON RD GORGAS LN E
HORTTER PL ANDERSON ST CUL DE SAC WEST
CLIVEDEN ST E CRITTENDEN ST STENTON AVE
JOHNSON ST ARDLEIGH ST STENTON AVE
DUVAL ST E ARDLEIGH ST CRITTENDEN ST
MILTON ST WASHINGTON LN E JOHNSON ST E

The contractor has confirmed that daytime milling operations will occur in the 4th Highway Bid#3964_G2023-00717.

Work will be completed in three separate phases: street milling, the adjustment of manhole covers and resetting of utility boxes, and final paving.  These activities will take place in separate construction phases spanning over the course of the next several months. Work for milling the old asphalt is anticipated to occur during the day shift and take approximately five (5) days per corridor. Work for adjusting manhole covers and resetting utility boxes will take place during the day shift and is anticipated to last two (2) to three (3) days per corridor. Lastly, operations for the final paving are anticipated to occur during the day and take approximately three (3) to five (5) day per corridor, weather dependent.

All work will take place during daytime hours from 7AM to 4PM.  The roadways will remain open with temporary flagging to direct traffic.

To complete the work, residents should expect some parking restrictions.  Temporary “No Parking” signs will be posted in advance of each scheduled activity.  Residents are urged to move their cars from the work sites when temporary “No Parking” signs are posted, so that vehicles are not towed.  In the event a car is towed, please contact the local Police District to determine its location.  Motorists are advised to allow extra time when traveling around the work areas.

While the Streets Department will make every effort to minimize disruption to traffic, residents are urged to plan and use alternative routes when traveling in these areas.  The Streets Department thanks residents in advance for their patience and cooperation as we work to improve City streets.

This street milling and manhole reset will be completed by Tony DePaul and paving will be completed by city forces.

For more information on the City’s Paving Program visit www.phila.gov/paving. For information on all City services, please call 311.

###