The Capital Program Office is pleased to announce that Phase 1 of renovations at Christy Recreation Center has reached substantial completion, marking a significant step in the multi-phase improvement of this vital Southwest Philadelphia community asset. Phase 1 represents an investment of $4.2 million toward creating safer, more accessible, and more engaging space for West Philadelphia residents. 

Building Upgrades 

Phase 1 improvements to the main building include: 

  • Installation of new window and door assemblies for the building and office 
  • Office reconfiguration to improve functionality 
  • Essential plumbing repairs in the office area 
  • Exterior painting and upgraded exterior lighting 

These enhancements strengthen building performance and create a more welcoming environment for staff and visitors. 

Site and Outdoor Improvements 

Several major exterior renovations were completed as part of Phase 1: 

  • Replacement of existing tennis courts with basketball courts 
  • Conversion of the former basketball courts into an outdoor play area 
  • Modifications to site entrances and walkways to ensure ADA-compliant vehicular and pedestrian access 
  • Installation of a new spray area near the pool zone, 
  • Landscaping upgrades and new site furnishings 
  • Construction of a subsurface modular stormwater infiltration basin 

Phase 1 also included preparation of the north site area to support future Phase 2 development. More to come soon!